Answer:
Total Overhead Variance= $500 unfavorable
Explanation:
The total overhead variance is the difference between actual overhead and the applied overhead.
Actual Overhead = Variable + Fixed= $9500 + $6050= $ 15,550
Budgeted Overhead for 30000 direct labor hours = $ 150,000
Applied Overhead for 3000 hours = 3000 *$5= $15000
Total Overhead Variance= Actual Overhead Less Applied Overhead
= $15,500- $ 15000= $500 unfavorable
As actual is greater than applied it is unfavorable.
Answer:
$550 unfavorable.
Explanation:
Total actual overhead = $9,500 + $6,050 = $15,550
Total predetermined overhead = Predetermined overhead rate * Standard hours = $5 * 3,000 = $15,000
Total overhead variance = $15,550 - $15,000 = $550 unfavorable.
Note: It is unfavorable because total actual is greater than total predetermined overhead.
Brownley Company has two service departments and two operating (production) departments. The Payroll Department services all three of the other departments in proportion to the number of employees in each. The Maintenance Department costs are allocated to the two operating departments in proportion to the floor space used by each. Listed below are the operating data for the current period: Service Depts. Production Depts. Payroll Maintenance Cutting Assembly Direct costs $ 20,400 $ 25,500 $ 76,500 $ 105,400 No. of personnel 15 15 45 Sq. ft. of space 10,000 15,000 The total cost of operating the Maintenance Department for the current period is:
Answer:
The total cost of operating the Maintenance Department for the current period is $29,580
Explanation:
In order to calculate The total cost of operating the Maintenance Department for the current period we would have to calculate first the Overhead allocated to Maintenance from Payroll department as follows:
Overhead allocated=Payroll overhead×(Maintenance payroll personnel/Total personnel)
Overhead allocated=$ 20,400×(15/15+15+45)
Overhead allocated=$4,080
Therefore, to calculate the The total cost of operating the Maintenance Department for the current period we would have to use the following formula:
Total cost of operating Maintenance Department=Overhead allocated+Direct overhead incurred
Total cost of operating Maintenance Department=$4,080+$25,500
Total cost of operating Maintenance Department=$29,580
The total cost of operating the Maintenance Department for the current period is $29,580
Which of the following is the most likely negative consequence of excessive change in an organization? Group of answer choices Staff being asked to do too much Staff being restricted to a single activity The operation of the organization at less than capacity The establishment of a system for prioritizing projects
Answer:
Staff being asked to do too much.
Explanation:
Excessive change in an organization is defined as a process when organizations pursue several differing, unrelated and sometimes changes that are conflicting simultaneously. It can also be, when an organization involves in introducing new changes before previous changes are being accomplished.
Additionally, when staffs or employees perceives change as being excessive, they react in various ways. Some of their reactions to excessive change includes;
• They become overwhelmed.
• Lack of motivation.
• They're stressed out.
• Frustration and anger builds among them.
• Inadequacy, uncertainty
and incompetence.
The lower level staffs and middle managers are most likely to experience, the negative consequence of excessive change in an organization because they're being asked to do too much.