Question 9 of 10
Stiviko's approved work plan included 4 technicians to create 200 web pages
over 5 days. What was the unit metric for the production work?
O A. 10 pages per technician per day
B, 40 pages per technician per day
C. 20 pages per technician per day
D. 400 web pages per week
SUBMIT
PREVIOUS
Answer:
A.
Explanation:
they make 40 a day because 200 / 5 = 40