Answer:
The question is very not detailed but I assume that because the path will finish does not mean that the whole thing/project will finish.
Step-by-step explanation:
Solve the following equa
8 (2v + 8) = 96
оа
v = 2
ii need help
Answer:
1
Step-by-step explanation:
64+32 =96 that'd how I got the answer
Answer:
[tex]{ \tt{8(2v + 8) = 96}} \\ { \tt{2v + 8 = 12}} \\ { \tt{2v = 4}} \\ { \bf{v = 2}}[/tex]
given circle o, what are the values of x and y?
Answer:
x = 38°
y = 90°
Step-by-step explanation:
x is an inscribed angle, so, 78/2=39
y is an inscribed angle of which connects two endpoints of the diameter, so y = 90°
Answered by GAUTHMATH
The number 6 is a solution to which of the following inequalities?
X - 13 > 7
6x < -12
6x > 32
21 + x < 28
Answer
6x<-12
Step-by-step explanation:
Answer:
There would be 2 answers in this case:
C. 6x > 32
and
D. 21 + x < 28
Step-by-step explanation:
A. Incorrect
6-13 = -7, and -7 is NOT greater than 7
B. Incorrect
6(6) = 36, and 36 is NOT less than -12.
C. Correct
6*6 = 36, which is greater than 32.
D. Correct
21+6 = 27, which is less than 28.
How much would $500 invested at 5% interest compounded continuously be worth after 4 years? Round your answer to the nearest cent
Answer:
$610.70
Step-by-step explanation:
[tex]a = pe^{rt}[/tex]
a = 500 [tex]e^{.05 * 4}[/tex]
a = $610.70
Consider the quadratic function f(x) = x2 - 5x + 6.
What are the values of the coefficients and constant in the function?
а
b
c
Answer:
a=1
b=-5
c=6
Step-by-step explanation:
ax^2+bx+c=0
Is the formula used for this question.
The given function is the same as y = 1x^2 + (-5x) + 6
Compare it to the form y = ax^2+bx+c, and we have the following:
a = 1
b = -5
c = 6
I do not understand any of this
Answer:
to get the slope. take the change of y axis value divide by the change of x axis value
pLZ HELPPPPPPPPPPPPPPPPPPPPPPPPP.
Answer:
x^4+4x^3+6x^2+7x+2
Express each of the following negative angles as its equivalent positive angle between 0°and360°
+120°
Answer:
Dilated pupils
Long periods of wakefulness
Loss of appetite
Overconfidence
Over-excitement
Paranoia
Runny nose or frequent sniffles
White powder around nostrils
Legal issues
Missing or being late to work
Financial problems
Mood swings
Irritability
Depression
What is the answer of this question?
Answer:
2 ( Option A )
Step-by-step explanation:
The given integral to us is ,
[tex]\longrightarrow \displaystyle \int_0^1 5x \sqrt{x}\ dx [/tex]
Here 5 is a constant so it can come out . So that,
[tex]\longrightarrow \displaystyle I = 5 \int_0^1 x \sqrt{x}\ dx [/tex]
Now we can write √x as ,
[tex]\longrightarrow I = \displaystyle 5 \int_0^1 x . x^{\frac{1}{2}} \ dx [/tex]
Simplify ,
[tex]\longrightarrow I = 5 \displaystyle \int_0^1 x^{\frac{3}{2}}\ dx [/tex]
By Power rule , the integral of x^3/2 wrt x is , 2/5x^5/2 . Therefore ,
[tex]\longrightarrow I = 5 \bigg( \dfrac{2}{5} x^{\frac{5}{2}} \bigg] ^1_0 \bigg) [/tex]
On simplifying we will get ,
[tex]\longrightarrow \underline{\underline{ I = 2 }}[/tex]
Solve for x. Round to the nearest tenth, if necessary.
Answer:
x = 63.9
Step-by-step explanation:
We have:
[tex]\frac{QR}{sin35}[/tex] = [tex]\frac{78}{sin90}[/tex]
=> QR × sin90 = 78 × sin35
=> QR × sin90 = 44.7
=> QR = 44.7
But, we also have: [tex]x^{2}[/tex] + [tex]QR^{2}[/tex] = [tex]78^{2}[/tex] <=> [tex]x^{2}[/tex] + [tex]44.7^{2}[/tex] = [tex]78^{2}[/tex] <=> [tex]x^{2}[/tex] = 6084 - 1998.09
=> [tex]x^{2}[/tex] = 4085.91
=> x = [tex]\sqrt{4085.91}[/tex] = 63.9211.. = 63.9
<3 Have a nice day!!
Using trial and improvement, find the solution between 5 and 6 for the following equation:
x
2
=
27
Give your answer rounded to 1 DP.
Answer:
2
Step-by-step explanation:
that is √ 14 which is 27 ×>44.2177
solve the logarithmic equation
[tex] log_{6}(2x - 6) + log_{6}x = 2[/tex]
Answer:
[tex]x=6[/tex]
Step-by-step explanation:
We want to solve the equation:
[tex]\displaystyle \log_6(2x-6)+\log_6x=2[/tex]
Recall the property:
[tex]\displaystyle \log_bx+\log_by=\log_b(xy)[/tex]
Hence:
[tex]\log_6(x(2x-6))=2[/tex]
Next, recall that by the definition of logarithms:
[tex]\displaystyle \log_b(a)=c\text{ if and only if } b^c=a[/tex]
Therefore:
[tex]6^2=x(2x-6)[/tex]
Solve for x. Simplify and distribute:
[tex]36=2x^2-6x[/tex]
We can divide both sides by two:
[tex]x^2-3x=18[/tex]
Subtract 18 from both sides:
[tex]x^2-3x-18=0[/tex]
Factor:
[tex](x-6)(x+3)=0[/tex]
Zero Product Property:
[tex]x-6=0\text{ or } x+3=0[/tex]
Solve for each case. Hence:
[tex]x=6\text{ or } x=-3[/tex]
Next, we must check the solutions for extraneous solutions. To do so, we can simply substitute the solutions back into the original equations and examine its validity.
Checking x = 6:
[tex]\displaystyle \begin{aligned} \log_{6}(2(6)-6)+\log_{6}6&\stackrel{?}{=} 2 \\ \\ \log_6(12-6)+(1)&\stackrel{?}{=}2 \\ \\ \log_6(6)+1&\stackrel{?}{=}2 \\ \\ 1+1=2&\stackrel{\checkmark}{=}2\end{aligned}[/tex]
Hence, x = 6 is indeed a solution.
Checking x = -3:
[tex]\displaystyle\begin{aligned} \log_6(2(-3)-6) + \underbrace{\log_6-3}_{\text{und.}} &\stackrel{?}{=} 2\\ \\ \end{aligned}[/tex]
Since the second term is undefined, x = -3 is not a solution.
Therefore, our only solution is x = 6.
Answer:
x = 6
Step-by-step explanation:
The given logarithmic equation is ,
[tex]\implies log_{6}(2x - 6) + log_{6}x = 2[/tex]
We can notice that the bases of both logarithm is same . So we can use a property of log as ,
[tex]\bf \to log_a b + log_a c = log_a {( ac)} [/tex]
So we can simplify the LHS and write it as ,
[tex]\implies log_{6} \{ x ( 2x - 6 )\} = 2 [/tex]
Now simplify out x(2x - 6 ) . We get ,
[tex]\implies log_6 ( 2x^2 - 6x ) = 2 [/tex]
Again , we know that ,
[tex]\bf \to log_a b = c , a^c = b [/tex]
Using this we have ,
[tex]\implies 2x^2 - 6x = 6^2 \\\\\implies 2x^2 - 6x -36 = 0 [/tex]
Now simplify the quadratic equation ,
[tex]\implies x^2 - 3x - 18 = 0 \\\\\implies x^2 -6x + 3x -18=0\\\\\implies x( x -6) +3( x - 6 ) = 0 \\\\\implies (x-6)(x+3) = 0 \\\\\implies x = 6 , -3 [/tex]
Since logarithms are not defined for negative numbers or zero , therefore ,
[tex]\implies 2x - 6 > 0 \\\\\implies x > 3 [/tex]
Therefore the equation is not defined at x = -3 . Hence the possible value of x is 6 .
[tex]\implies \underline{\underline{ x \quad = \quad 6 }}[/tex]
Someone tell me where everyone is going right please !!
Answer:
1min = 0.25miles
5.25miles / 0.25miles = 25 = 25minutes
Step-by-step explanation:
Hope this is right I'm not the best at worded time/distance math questions.
9514 1404 393
Answer:
0 ≤ t < 52.5 minutes
Step-by-step explanation:
Riko will be behind Yuto until her distance traveled matches his. That is, she will be behind for ...
0.35t < 5.25 +0.25t
0.10t < 5.25
t < 52.5
Riko will be behind Yuto on the interval 0 ≤ t < 52.5 minutes.
_____
Additional comment
distance = speed × time
Here, time is measured from when Riko starts riding. In addition to the 5.25 miles that Yuto has already gone, his distance will be the product of his speed (0.25 mi/min) and the travel time (t min). Then Yuto's total distance is 5.25+0.25t miles. The speed×time product is also used to find Riko's distance traveled. In her case, it is 0.35t miles.
what is the solution to 4 1/5 x (1 1/9 x 3)
Answer:
14
Step-by-step explanation:
[tex]4 \frac{1}{5} \times (1 \frac{1}{9} \times 3) \\\\= \frac{21}{5} \times ( \frac{10}{9} \times 3)\\\\=\frac{21}{5} \times( \frac{10}{3})\\\\= \frac{21 \times 10}{ 5 \times 3}\\\\=7 \times 2 \\\\= 14[/tex]
Which number line model represents the expression -2+(-7)
Answer:
B
Step-by-step explanation:
Start at zero.
Go 2 units left to -2.
Then go another 7 units left to add -7.
Answer: B
factor completely 8y2 + 6y + 1
Answer:
Step-by-step explanation:
8y²+6y+1
=8y²+4y+2y+1
=4y(2y+1)+1(2y+1)
=(2y+1)(8y+1)
the lines given by the equations y=6x and y=6x+2 are ____
They are parallel, as shown by the graph.
What are the zeros of the polynomial function f(x) = x(x + 5)(x – 8)?
–5, 8
0, –5, 8
5, –8
0, 5, –8
Answer:
Option B is answer.
Step-by-step explanation:
Hey there!
Given;
f(X) = X(X+5)(x-8)
According to the factor theorem, f(X) = 0;
Or, X(X+5)(x-8) = 0
Either;
x = 0
Or;
(x+5)= 0
X = -5
Or;
(x-8)= 0
x = 8.
Therefore, the zeros of the polynomial are: 0,-5,8.
Hope it helps!
solve the equation x + 5 = 12
Answer:
x = 7
Step-by-step explanation:
x + 5 = 12
Subtract 5 from both sides
5 - 5 cancels out
12 - 5 = 7
We're left with x = 7
Find the TWO integers whos product is -12 and whose sum is 1
m
Answer:
[tex] \rm Numbers = 4 \ and \ -3.[/tex]
Step-by-step explanation:
Given :-
The sum of two numbers is 1 .
The product of the nos . is 12 .
And we need to find out the numbers. So let us take ,
First number be x
Second number be 1-x .
According to first condition :-
[tex]\rm\implies 1st \ number * 2nd \ number= -12\\\\\rm\implies x(1-x)=-12\\\\\rm\implies x - x^2=-12\\\\\rm\implies x^2-x-12=0\\\\\rm\implies x^2-4x+3x-12=0\\\\\rm\implies x(x-4)+3(x-4)=0\\\\\rm\implies (x-4)(x+3)=0\\\\\rm\implies\boxed{\red{\rm x = 4 , -3 }}[/tex]
Hence the numbers are 4 and -3.
Answer:
-3,4 are the TWO integers whos product is -12 and whose sum is 1.
Step-by-step explanation:
-3×4=12
-3+4=1
The 9th term of an arithmetic progression is 3+3p and the sum of the first four terms is 2p-10, where p is constant. Given that the common difference is 2, find the value of p.
Answer:
3
Step-by-step explanation:
Let's find the first term in terms of p.
So an arithmetic sequence is a linear relation.
That means it will have the same slope no matter the pair of points used. We are given the slope, the common difference, is 2. We are going to use point (9, 3+3p) and (1, t(1)) along with m=2 to find t(1).
[t(1)-(3+3p)]/[1-9]=2
Simplify denominator
[t(1)-(3+3p)]/[-8]=2
Multiply both sides by -8
t(1)-(3+3p)=-16
Add (3+3p) on both sides
t(1)=-16+3+3p
Combine like terms
t(1)=-13+3p
This means we can find the next term by adding 2 this.
t(2)=-11+3p
Let's find the next term by adding 2 this.
t(3)=-9+3p
Finally we can find the 4th term by adding 2 to this
t(4)=-7+3p
We are given the sum of the first 4 terms is 2p-10. So we can write:
-13+3p+-11+3p+-9+3p+-7+3p=2p-10
Combine like terms on left
12p-40=2p-10
Subtract 2p on both sides
10p-40=-10
Add 40 on both sides
10p=30
Divide both sides by 10
p=3.
-----------------
Checking:
t(1)=-13+3p=-13+3(3)=-13+9=-4
t(2)=-11+3p=-11+3(3)=-11+9=-2
t(3)=-9+3p=-9+3(3)=-9+9=0
t(4)=-7+3p=-7+3(3)=-7+9=2
----sum of the first 4 is -4
And 2p-10 at p=3 gives 2(3)-10=6-10=-4
So this part checks out
In general, the pattern that those 4 terms I wrote out follow t(n)=(-13-2)+2n+3p. I know this because the 0th term would have been (-13-2)+3p and this part goes up by 2 each time. The plus 3p part doesn't change.
Anyways t(9)=(-13-2)+2(9)+3p=-15+18+3p=3+3p. And this part looks good too.
Mark had 3/2 cans of paint and used 1/2 cans for his room. What fraction of the paint did he use
Help I’m slowww
Answer:
1/3 fraction of whole paint is used by mark
Step-by-step explanation:
Mark used 1/2 out of 3/2 cans.
[tex]\frac{1}{2}[/tex] ÷ [tex]\frac{3}{2} = \frac{1}{2}*\frac{2}{3}=\frac{1}{3}[/tex]
P=(2,3,5,7) Express it in description method and in rule method.
Answer:
prime number between 1 to7
The description of set P is the set of prime numbers less than or equal to 7 and the rule is {x | x is a prime number less than or equal to 7}
How to describe the set of P?The set P is given as:
P = {2,3,5,7}
Note that the numbers are prime numbers.
This means that the description of set P is the set of prime numbers less than or equal to 7
The rule form of the set would be:
P = {x | x is a prime number less than or equal to 7}
Read more about sets at:
https://brainly.com/question/1563195
#SPJ2
6. Don Juan compro un terreno con las dimensiones que se muestran en la figura el cual se va acondicionar para realizar eventos sociales, por lo que desea instalar césped en la region sombreada. ¿Cuantos metros cuadrados de césped requiere? Considera rt=3.14 16 m O 50 24 m2 0 205 76 m2 256 00 m2 0 5504 m2
Answer:
Not sure but I think it might be A
Step-by-step explanation:
Took the test
Marc puts 28 liters of water into a tub and 6 liters of water into a bucket. Then, he pours both containers into a tank.
Answer:
34
Step-by-step explanation:
The interior angle of a polygon is 3degrees greater than the exterior angle.find the sum of the angles of the polygon
Step-by-step explanation:
We know that the sum of angle around a point is 180° . Therefore let the first angle be x then second will be x + 3 .
According to the Question ,
> x + x + 3 = 360°
> 2x = 357=
> x = 357°/2
> x = 178.5°
1. Write down the gradient of the line joining the points (2m, n) and (3, -4).
2.Find the value of n if the line is parallel to the X-axis
3.Find the value of m if the line is parallel to the Y-axis.
Answer:
Step-by-step explanation:
1 . ( n + 4 ) / ( 2m - 3 )
The gradient (slope) is
= ( change in y direction ) / ( change in x direction )
= ( n - (-4) ) / ( 2m - 3 )
= ( n + 4 ) / ( 2m - 3 )
2.
A line parallel to the x-axis will always have the equation of y = #. This is because all along that line, every value of x, y will still equal the same number. For example, a line parallel to the x-axis that crosses the y-axis at 2, will be y = 2. If it is in the negative range, it's the same concept, for example if it crossed the y-axis at -4, the equation would be y = -4.
Example - Computational Knowledge Engine
3.
To understand the slope of a line parallel to y axis, let us consider the figure given below.
1 . The gradient (slope) is ( n + 4 ) / ( 2m - 3 )
2. n = -4
3. m is not defined.
What is Slope?A line's slope is determined by how its y coordinate changes in relation to how its x coordinate changes. y and x are the net changes in the y and x coordinates, respectively. Therefore, it is possible to write the
change in y coordinate with respect to the change in x coordinate as,
m = Δy/Δx where, m is the slope
Given:
points (2m, n) and (3, -4).
1 . The gradient (slope) is
= ( change in y direction ) / ( change in x direction )
= ( n - (-4) ) / ( 2m - 3 )
= ( n + 4 ) / ( 2m - 3 )
2. A line parallel to the x-axis will always have the equation of y = x.
The line is therefore horizontal so gradient = 0
(n+4) / (2m-3)= 0
n = -4
(iii) Find the value of m if the line is parallel to the y-axis
(n+4) / (2m-3)= gradient
(n+4) / (2m-3)= 1
We know n = -4 from part (ii) then
(-4+4) /(2m-3)= 1
0/(2m-3) = 1
0 = 1 The 'm' vanishes
Hence, m is not defined.
Learn more about slope here:
https://brainly.com/question/3605446
#SPJ2
Help me with this problem
Answer:
The answer is 180 - 65
Step-by-step explanation:
We got 180, because that is the number of degree's in a line
so 180 - 65 is 115 degrees, that's your answer :)
A u B u C A=(a,b,c,d,e) B=(d,e,f,g,h,i) C=(a,e,i,o,u) help class 8
Answer:
If U = { a, b, c, d, e, f, g, h} , find the complements of the following sets:(i) A = {a, b, c} (ii) B = {d, e, f, g} (iii) C = {a, c, e, g} (iv) D = { f, g, h, a}
Answer:
if;A= { a,b,c,d,e}
B= {d,e,f,g,h,i}
C= {a,e,i,o,u}
AuBuC = {a,b,c,d,e,f,g,h,i,o,u}
HAVE A NİCE DAY
Step-by-step explanation:
GREETİNGS FROM TURKEY ¯ツ
I did 70 jumping jacks in 1 minute.
Which is the dependent variable? Which is the independent variable?
Write an equation that represents the relationship between the time you spent doing the activity and the amount of the activity you completed.
Answer:
in jh ynhtym
hunt ghb JBL iggmmjuu ki ju nu j